- API Operator Qualification Conference
- Workshop on Pipeline Integrity Management
- DOT To Hold Two Meetings About Drug and Alcohol Testing Procedures
- Bush Places Moratorium on Regulations
- FERC Meeting
- Pipeline Integrity Management Public Meetings
- Washington State Best Practices Report
- Help Wanted
- Regulatory Watch: Key Dates & Deadlines
- Conference News
- PSI Training Schedule
API Operator Qualification Conference
API will host a two-day Pipeline Operator Qualification Conference, February 14-15, 2001 at Sheraton Houston Brookhollow, 3000 North Loop West Houston, TX. This conference will feature speakers from industry and TSI, and will include the following topics:
- Introduction to API RP 1161 – Guidance Document for Qualification of Liquid Pipeline Personnel
- Discussion of the API/ National Center for Construction Education and Research (NCCER) Alliance OQ Program
- Discussion of OQ implementation issues, with recommended strategies.
The conference web page can be found at http://www.api.org/training/Conferences/OQconference.htm. RCP is one of the corporate sponsors for this conference. We hope to see you there!
Workshop on Pipeline Integrity Management
RCP is conducting a 3 day workshop on Pipeline Integrity Management on Tuesday, March 6-8, 2001 at our Houston office. We will review the new federal rulemaking for Pipeline Integrity Management in High Consequence Areas (see our December 2000 pipeline newsletter). This final rule specifies regulations to assess, evaluate, repair and validate through comprehensive analysis the integrity of hazardous liquid pipeline segments that, in the event of a leak or failure, could affect populated areas, areas unusually sensitive to environmental damage and commercially navigable waterways. This final rule takes effect March 31, 2001. We will also review and discuss the proposed pipeline integrity management rulemaking for the State of Texas, which will apply to ALL intrastate pipeline operators. The workshop web page can be found at http://www.your-rcp.com/dotseminar2001.htm
DOT To Hold Two Meetings About Drug and Alcohol Testing Procedures
The U.S. Department of Transportation (DOT) is scheduling two one-day public meetings to provide interested parties a detailed overview of the Department's revised drug and alcohol testing procedures, published in the Federal Register on December 19, 2000 ( 65 Fed. Reg. 79462 ). [Insert link] The meeting notice is published at 66 Fed. Reg. 7590, Jan. 24, 2001.
The meetings are being held to provide the transportation industry and other interested parties a more in depth overview of the changes in the new rule and to clarify to the attendees issues, which they may raise at the meetings. Some of the major changes in the rule will be addressed in detail.
The public meetings will be held on February 21 and 22, 2001, at 9:00 am-5:30 pm on both days, at the Federal Aviation Administration (FAA) Auditorium, 3rd Floor Center, 800 Independence Avenue, SW., Washington, DC 20591. The second meeting will be a repetition of the previous day. Specifically, the same presentations will be repeated by the same DOT staff members. Individuals should attend only one of the meetings, not both. Both meetings will have limited seating capacity due to physical constraints of the facilities. Registered attendees will receive priority.
For general meeting information and to register for one of the meetings, contact Minnie McDonald or Don Shatinsky at the U.S. Department of Transportation (DOT), Office of Drug and Alcohol Policy and Compliance, 400, 7th Street, SW., Room 10304, Washington, DC 20590, (202) 366-3784, fax (202) 399-3897, e-mail: minnie.mcdonald@ost.dot.gov.
All attendees must register with DOT for these meetings. All attendeesshould provide the name, name of alternate if the possibility exists that the primary registrant may not attend, full mailing address, company, agency, or association which you represent (if any), telephone number (in case the address is not legible or additional information is needed), e-mail address (optional), and which session you will be attending (i.e., February 21 or 22).
Bush Places Moratorium on Regulations
On January 24, 2001, President Bush placed a moratorium on new and proposed regulations, summarized below.
Subject to any exceptions the Director or Acting Director of the Office of Management and Budget (the "OMB Director") allows for emergency or other urgent situations relating to health and safety:
- Send no proposed or final regulation to the Office of the Federal Register (the "OFR") unless and until a department or agency head appointed by the President after noon on January 20, 2001, reviews and approves the regulatory action.
- With respect to regulations that have been sent to the OFR but not published in the Federal Register, withdraw them from OFR for review and approval as described in paragraph 1.
- With respect to regulations that have been published in the OFR but have not taken effect, temporarily postpone the effective date of the regulations for 60 days.
This moratorium will delay the effective date of the Pipeline Integrity Management Rule for pipelines of more than 500 miles to May 31, 2001, and will delay the issuance of the proposed rulemaking on Integrity Management for systems less than 500 miles. The complete order is available on RCP's website at 66_FR_07702_012401_Rule_Moratorium.RTF.
FERC Meeting
FERC Meeting: Notice of Third Interstate Natural Gas Facility-Planning Seminar:
The Federal Energy Regulatory Commission Office of Energy Projects will hold the third in a series of public meetings around the country for the purposes of exploring and enhancing strategies for constructive public participation in the earliest stages of natural gas facility planning. This meeting will be held in Tampa, Florida on Thursday, February 15, 2001. FERC is inviting interstate natural gas companies; Federal, state and local agencies; landowners and non-governmental organizations with an interest in developing a new way of doing business to join in this effort.
Participants will discuss the facility planning process, not the merits of any pending or planned pipeline projects. The staff of the Commission's Office of Energy Projects will give a briefing on the results of our first two seminars in Albany, NY and Chicago, IL, including problems that were identified and potential solutions that were offered in the seminars.
The meeting will be held at the Holiday Inn City Centre, located in Tampa, Florida. The meeting is scheduled to start at 9:30 a.m. and finish at 4 p.m. If you plan to attend, please email gasoutreach@ferc.fed.us by February 6, 2001. Or, you can respond via facsimile to Pennie Lewis-Partee at 202-208-0353. Please include in the response the names, addresses, and telephone numbers of all attendees from your organization. FERC will send an acknowledgment of your request. Please consider issues and/or questions you would like to have addressed at the meetings and email them to FERC.
Pipeline Integrity Management Public Meetings
OPS will host a three-day public meeting on pipeline integrity management issues on February 12-14, 2001, at the Crystal City Marriott, 1999 Jefferson Davis Highway, Arlington, VA, 22202, 703-413-5500. For further information, contact Beth Callsen (tel: 202-366-4572; beth.callsen@rspa.dot.gov). You can read comments and other material in the docket on the Internet at: http://dms.dot.gov. Topics to be discussed each day are listed below.
Day 1: February 12, 2001 from 9 a.m. to 4 p.m. – Gas Pipeline Integrity Presentations will be made on each of these subject areas:
- Considerations for defining HCAs affected by gas pipelines
- Evaluation of design factors currently used for gas transmission pipelines
- Evaluation of performance history and experience with the impact zone in gas transmission failures
- Integrity management best practices and relationship between incident causes and industry practices
- Options for various forms of direct assessment of the integrity of gas pipelines; their costs and effectiveness
- Basis for establishing test intervals
- Appropriateness of distinguishing between pipelines on basis of pressure
- Status of research activities
- Status of development of new national consensus standards
Day 2: February 13, 2001, from 9 a.m. to 4 p.m. – Communications With the Public
Because communications with the public is an important part of a pipeline integrity management program, OPS is examining the need for standards for how operators are to communicate with State and local officials and the public about results of risk assessment processes and measures to prevent and mitigate damage to pipelines in case of a failure. OPS seeks comment on how State and local officials and the public could use and benefit from risk assessment information, how the consequences of potential pipeline failures should be characterized, how risk control actions should be described, and what operational information would be meaningful. To provide OPS input on both the content and optimal delivery of pipeline information, OPS formed the Integrity Management Communications Work Group. This nine-member group includes balanced representation of government, industry, and public interest stakeholders. At the public meeting, the Work Group will report the status of its discussions on the following topics:
- Proposed information to be communicated
- Expected utility of that information to the end user
- Feasibility of collecting/reporting that information
- Summary of any issues or debates concerning public access to that information
Presentations from members of the public will further explore communication needs and options.
Day 3:February 14, 2001, from 9 a.m. to 12 noon – In-Depth Integrity Management Discussions
To ensure full consideration of all issues relating to gas pipeline integrity, attendees are invited to participate in a more in-depth and interactive treatment of topics raised on Day 1. These unstructured discussions will utilize an informal roundtable format.
Washington State Best Practices Report
The Washington Utilities and Transportation Commission (WUTC) submitted a Best Practices Damage Prevention Report to the legislature on December 22, 2000. The Washington State Pipeline Safety Act identified one-call systems as a key ingredient to preventingdamage to underground utilities, including pipelines. Section 16 of the bill directed the Utilities and Transportation Commission to make recommendations to the Legislature regarding one-call systems inthe state. Theirreport contains recommendations regarding minimum standards and best practices for one-call locator services that were derived from a series of stakeholder workshops held in the summer and fall of 2000. The basis for discussion during these workshops was a 1999 report initiated by the U.S. Department of Transportation's Office of Pipeline Safety, called "Common Ground – Study of One-Call Systems and Damage PreventionBest Practices." The WUTC report may be found on the Commission's website located at: http://www.wutc.wa.gov. Just click on the "Pipeline Safety" tab on theCommission's homepage and then look for the "Best Practices Report" hyperlink.
Acquiring a pipeline?
RCP can provide due diligence audits to help you ensure that potential compliance issues have been addressed before the sale is final.
Pending Audits?
Has the DOT notified you of a pending audit? RCP can provide confidential internal auditing to help ensure that your facilities are up to the agency's latest standards.
Help Wanted
Know someone with regulatory expertise who is interested in full or part time work? Our recruiting coordinator would be glad to get their resume! Have them sent to chandra@your-rcp.com, or FAX to 713-655-8083.
Visit Regulatory Compliance Partners on the Web at
or call us at 1-888-RCP-X-YES to see what we can do for you.
Ongoing Resources
These articles are maintained and updated as new information becomes available.
Regulatory Watch: Key Dates & Deadlines
Welcome to Regulatory Watch! In this monthly update, we’ll keep you informed on proposed rule comment periods, effective dates, and upcoming deadlines for various compliance requirements.
Proposed Rule Stage
Administrative Rulemaking Regulatory Procedures
Amendments to Liquefied Natural Gas Facilities
Breakout Tank
Oil Spill Response Plans, Accident Notifications, Inspections and Investigations and other Miscellaneous Pipeline Safety Changes
Pipeline Operational Status
Repair Criteria for Gas and Hazardous Liquid Pipelines
Safety of Carbon Dioxide and Hazardous Liquid Pipelines
Final Rule Stage
Coastal Ecological Unusually Sensitive Areas
Cost Recovery for Siting Reviews for LNG Facilities
Gas Pipeline Leak Detection and Repair
Safety of Gas Distribution Pipelines and Other Pipeline Safety Initiatives
Sprint I & II Update
To further the Administration’s deregulatory policies, PHMSA has published in today’s Federal Register twenty-eight (28) separate rulemaking actions affecting the pipeline safety regulations (PSR; Parts 190-199). Click here to access the documents.
| Rulemaking | Description | Stage | Code |
|---|---|---|---|
| Pipeline Safety: Rationalize Special Permit Conditions | PHMSA proposes to amend its special permit procedures to ensure permit conditions are directly tied to the specific pipeline safety regulations being waived. | NPRM | 49 CFR Part 190 |
| Pipeline Safety: Rationalize Calculation of Regulatory Filing and Compliance Deadlines | PHMSA will clarify that regulatory filing and compliance deadlines falling on weekends or Federal holidays automatically move to the next business day. | DFR | 49 CFR Part 190 |
| Pipeline Safety: Adjust Annual Report Filing Timelines | PHMSA will amend annual reporting requirements to move the gas pipeline annual report submission deadline from March to June. | DFR | 49 CFR Part 191 |
| Pipeline Safety: Property Damage Definition for Incident Reporting | PHMSA will clarify incident reporting property damage calculations for gas pipelines and update hazardous liquid accident reporting thresholds using inflation-adjusted criteria. | DFR | 49 CFR Parts 191 & 195 |
| Pipeline Safety: Exception for In-Plant Piping Systems | PHMSA proposes to clarify that in-plant piping systems are not subject to federal pipeline safety regulations. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Codify Enforcement Discretion on Incidental Gathering Lines | PHMSA proposes to codify enforcement discretion clarifying that restrictions on the historical incidental gathering line exemption apply only to newly constructed lines. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Eliminate Burdensome Coating Assessment Deadlines | PHMSA proposes to replace prescriptive deadlines for coating damage assessments and remediation with a requirement that activities be completed before the pipeline is placed in service. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Atmospheric Corrosion Reassessment for Pipeline Replacements | PHMSA proposes to remove the 3-year reassessment interval following replacement of atmospheric corrosion defects and allow use of the standard 5-year reassessment interval. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Harmonize Class Change Pressure Test Requirements | PHMSA proposes to reduce the minimum pressure test duration following certain class location changes from 8 hours to 4 hours, aligning with existing Subpart J requirements. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Clarify MAOP Reconfirmation Testing Records | PHMSA will issue a technical correction clarifying that operators may use pre-1970s pressure test records when reconfirming MAOP under §192.624. | Final Rule | 49 CFR Part 192 |
| Pipeline Safety: Remote Sensing Technologies for ROW Patrols | PHMSA will explicitly allow right-of-way patrols to be conducted using unmanned aircraft systems, satellites, and other remote sensing technologies. | DFR | 49 CFR Parts 192 & 195 |
| Pipeline Safety: Technical Standards Updates and Amendments | PHMSA will update incorporated standards and make technical amendments in response to an industry petition for reconsideration. | Final Rule | 49 CFR Part 192 |
| Pipeline Safety Program: Update of Standards Incorporated by Reference | PHMSA issued multiple direct final rules updating incorporated industry consensus standards used throughout Parts 192 and 195, replacing outdated editions with current versions. | Multiple DFRs | 49 CFR Parts 192 & 195 |
The following is a summary of the 40 rulemakings that PHMSA published in the Federal Register on April 24, 2026. If any adverse comment is received to a DFR PHMSA must rescind the rule and repropose. Click here to access the documents.
| Rulemaking | Description | Stage | Code |
|---|---|---|---|
| Pipeline Safety and Hazardous Materials Safety: Amendments to PHMSA Procedural Regulations | PHMSA proposed miscellaneous amendments to procedural regulations governing informal rulemaking for both pipeline safety and hazardous materials programs. | NPRM | 49 CFR Part 190 |
| Pipeline Safety: Interpretation Request Procedures | PHMSA amended interpretation procedures to require publication of interpretation requests on its website and provide an opportunity for public comment. | Final Rule | 49 CFR Part 190 |
| Pipeline Safety: Declaratory Order Procedures | PHMSA established formal procedures for issuing declaratory orders through a new section in Part 190. | Final Rule | 49 CFR Part 190 |
| Pipeline Safety: Consent Orders | PHMSA clarified that consent agreements may be used to resolve enforcement actions, including cases involving civil penalties. | Final Rule | 49 CFR Part 190 |
| Pipeline Safety: Adjustment to OPID Notifications for Construction | PHMSA proposed adjusting the inflation-based threshold that triggers OPID notifications for certain construction and facility modification activities. | NPRM | 49 CFR Part 191 |
| Pipeline Safety: Eliminating Limitations on Welders and Welding Operators | PHMSA proposed allowing welders qualified through non-destructive testing methods to perform compressor station welding activities currently subject to additional restrictions. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Material Properties Verification During MAOP Reconfirmation | PHMSA proposed clarifying that material testing at pressure test manifold sites is not required when traceable, verifiable, and complete material records already exist. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Electronic Retention of Part 194 Response Plans | PHMSA amended regulations to allow operators to maintain electronic copies of response plans instead of paper copies. | DFR | 49 CFR Part 194 |
| Pipeline Safety: Remote Monitoring of Rectifiers | PHMSA proposed allowing remote monitoring technologies for rectifiers used in external corrosion control programs. | NPRM | 49 CFR Part 195 |
| Pipeline Safety: Clarifying Hazardous Liquid High-Consequence Area Designations | PHMSA amended HCA guidance to clarify spill considerations in agricultural fields and reorganize threat identification guidance. | DFR | 49 CFR Part 195 |
| Pipeline Safety: Timeframe to Make Rupture-Mitigation Valves Operational | PHMSA proposed extending the deadline for placing rupture-mitigation valves into operation from 14 days to 90 days after a pipeline enters service. | NPRM | 49 CFR Part 192 |
| Pipeline Safety: Hazardous Liquid Valve Maintenance Schedule | PHMSA proposed allowing operators to implement risk-based valve maintenance schedules, subject to a maximum inspection interval of one year. | NPRM | 49 CFR Part 195 |
| Pipeline Safety: Property Damage Definition for Incident Reporting | PHMSA proposes revising property damage thresholds for reportable gas and hazardous liquid pipeline incidents and clarifying applicability to telephonic notifications. | NPRM | 49 CFR Parts 192 & 195 |
| Pipeline Safety: Remote Sensing Technologies for ROW Patrols | PHMSA proposes clarifying that unmanned aerial systems, satellites, and other remote-sensing technologies may be used to satisfy right-of-way patrol requirements. | NPRM | 49 CFR Parts 192 & 195 |
| Pipeline Safety: Adjust Annual Report and NPMS Filing Timelines | PHMSA proposes extending annual report and NPMS submission deadlines for gas pipeline and storage operators to June 15 each year. | NPRM | 49 CFR Part 191 |
| Pipeline Safety: Editorial Corrections and Clarifications | PHMSA issued multiple final rules correcting editorial errors, updating references, removing obsolete submission methods, and improving regulatory clarity. | Final Rules | Various |
| Pipeline Safety: Update of Standards Incorporated by Reference | PHMSA issued multiple direct final rules updating incorporated industry consensus standards, including NFPA, ASTM, MSS, NACE, and ASME standards. | Multiple DFRs | 49 CFR Parts 192 & 195 |
Have questions about an upcoming deadline? Please reach out to Jessica Foley for assistance!
Conference News
Pipeline Pigging and Integrity Management Conference
The 39th International Pipeline Pigging & Integrity Management Conference (PPIM) will take place at the George R. Brown Convention Center in Houston. The event brings together pipeline operators, engineers, and industry professionals to explore advancements in pipeline inspection, integrity management, risk assessment, and emerging technologies.…
RCP Team Attending
Heather RoarkSales & Marketing Coordinator
Jessica FoleyVice President🎤 Featured Presentations
Topic to be determined

PSI Training Schedule

| Date | Training Course | Price | Registration |
|---|---|---|---|
| Nov 17 – Nov 19, 2026 | DOT Pipeline Compliance Workshop | $2,150 | SOLD OUT |
| Feb 16 – Feb 18, 2027 | Pipeline Safety Audit Training | $2,150 | Register → |
| Feb 23 – Feb 25, 2027 | Advanced Pipeline Risk Assessment Workshop | $2,150 | Register → |
| Mar 23 – Mar 25, 2027 | DOT Pipeline Compliance Workshop | $2,150 | Register → |
WEBINAR RECORDING!
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition
RCP and the Pipeline Safety Institute offered a free webinar exploring the 2nd Editions of API RP 1170, Design and Operation of Solution-mined Salt Caverns Used for Natural Gas Storage and API RP 1171, Functional Integrity of Natural Gas Storage in Depleted Hydrocarbon Reservoirs and Aquifer Reservoirs. Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!
You asked and we listened!
Advanced DOT Pipeline Compliance Workshop is on the calendar!
This intensive and interactive 3-day, in-person workshop is designed for those who have previously completed our DOT Pipeline Compliance Workshop and are ready to take their knowledge to the next level.
New Workshop Alert!
Prepare Your Team for Pipeline Safety Audits with Confidence!
Our 3-day Pipeline Safety Audit Workshop is tailored for professionals responsible for the safe operation of hazardous liquid and natural gas pipelines. Designed for groups of 10-15 participants, this interactive training…
On-Site Training Request
We have conducted on-site training for oil and gas companies for over 25 years and can provide customized workshops for companies with groups of five or more.
We would welcome the opportunity to discuss our services with you.
Sincerely,
![]()
W. R. (Bill) Byrd, PE
President
RCP Inc.![]()
- API Operator Qualification Conference
- Workshop on Pipeline Integrity Management
- DOT To Hold Two Meetings About Drug and Alcohol Testing Procedures
- Bush Places Moratorium on Regulations
- FERC Meeting
- Pipeline Integrity Management Public Meetings
- Washington State Best Practices Report
- Help Wanted
- Regulatory Watch: Key Dates & Deadlines
- Conference News
- PSI Training Schedule


