PHMSA Final Rule on Increasing MAOP for Gas Transmission Pipelines

[Docket ID PHMSA-2005-23447]

The Pipeline and Hazardous Materials Safety Administration (PHMSA) issued its final rule amending the pipeline safety regulations to prescribe safety requirements for the operation of certain gas transmission pipelines (49 CFR 192) at pressures based on higher operating stress levels. The result is an increase of maximum allowable operating pressure (MAOP) over that currently allowed in the regulations. This final rule updates regulatory standards to reflect improvements in pipeline materials, assessment tools, and maintenance practices, which together have significantly reduced the risk of failure in steel pipeline fabricated and installed over the last twenty-five years. The final rule would apply to both new and existing pipelines, and would allow use of an established industry standard for the calculation of MAOP, but limit application of the standard to pipelines posing a low safety risk based on location, materials, and construction.

PHMSA has previously granted special permits on a case-by-case basis to allow operation of particular pipeline segments at a higher MAOP than currently allowed under the design requirements. With the publication of this final rule, this case-by-case approach to approving operation under a special permit at higher operating stress levels is no longer needed, and PHMSA will terminate its review of any pending applications. Under the final rule, several types of segments will not qualify for the higher MAOP:

  • Segments in densely populated Class 4 locations
  • Segments of grandfathered pipeline already operating at a higher stress level but not constructed in accordance with modern standards.
  • Bare pipe.
  • Non-steel pipe
  • Pipe with wrinkle bends
  • Pipe experiencing failures indicative of a systemic problem, such as seam flaws, during the initial hydrostatic testing.
  • Pipe manufactured by certain processes, such as low frequency electric welding process.
  • Segments which cannot accommodate internal inspection devices.

The rulemaking imposes new and additional design, construction, and operation standards to pipe operating at the higher MAOP, including:

  • Incorporating by reference ASTM Designation: A578/A578M-96 (Reapproved 2001) “Standard Specification for Straight-Beam Ultrasonic Examination of Plain and Clad Steel Plates for Special Applications”.
  • Prescribing additional design requirements in §192.112.
  • Prescribing additional construction requirements, including rigorous quality control and inspections, in §192.328.
  • Specifying additional operations, maintenance, testing, and notification requirements.

PHMSA made some revisions to the final rule from the provisions proposed in the NPRM on March 12, 2008. Some of the revisions include:

  • Use of an alternate International Institute of Welding Carbon Equivalent (CE) formula.
  • Allow a long-term coating integrity monitoring program to be used as a basis for allowing pipe temperatures in excess of 120 degrees Fahrenheit. Operators must submit their programs to the PHMSA pipeline safety regional office for review before pipeline segments may be operated at alternative MAOP at these higher temperatures.
  • Allow a root cause analysis of any failures as a way of justifying qualification of a pipeline segment.
  • Revised the required patrol frequency from 26 patrols per year, to once per month, at intervals not to exceed 45 days.

Effective date of the final rule is November 17, 2008. For a copy of PHMSA’s Final Rule on Increasing MAOP for Gas Transmission Pipelines, contact Jessica Roger.

Minerals Management Service (MMS) Damage Reporting Changes

[Docket ID MMS-2008-OMM-0001]

Effective December 1, 2008, the MMS is amending its regulations to require lessees, lease operators, and pipeline right-of-way holders to submit a report if a facility or pipeline is damaged by a hurricane or other natural phenomena. The final rule also requires operators to provide assessment information on the structural integrity of Outer Continental Shelf platforms; information on the use of unbonded flexible pipe for pipelines; and additional information when installing pipeline risers on floating platforms. The rule also incorporates an industry-developed standard concerning the in-service inspection of mooring hardware for floating drilling units. These changes will allow MMS to better regulate the safety of the oil and gas infrastructure, and to promptly assess damage resulting from hurricanes or other natural phenomena.

For additional information about this rulemaking, or for assistance in developing and managing the offshore inspection requirements required by MMS for offshore pipelines, contact Jessica Roger.

Texas Pipeline Safety Regulations – Proposed Revisions

The Texas Railroad Commission (TRRC) has proposed several revisions to 16 TAC Chapter 8 – Pipeline Safety Regulations. The amendments include:

  • New language to address onshore gas production pipeline facilities. If finalized in current form, onshore production lines in Class 2, 3 and 4 locations, beginning at the first point of measurement and ending as defined by 49 CFR Part 192 as the beginning of an onshore gathering line would be regulated and follow similar requirements for regulated gas gathering pipelines.
  • Removal of gas gathering pipeline facilities from the state required Pipeline Integrity Management regulations. If finalized in current form, gas gathering pipelines would be exempt from future assessments. However, gas transmission pipelines will still be required to follow the state integrity management requirements, in addition to any applicable federal integrity management requirements.

Comments on the proposal are due by November 10th and may be submitted online at http://www.rrc.state.tx.us/rules/commentform.php or by email to rulescoordinator@rrc.state.tx.us. For a complete copy of TRRC's proposed revisions, contact Jessica Roger.

Save the Dates!

RCP DOT Workshops in 2009

February 25 & 26 (Wednesday & Thursday) – Houston, TX

June 2 & 3 (Tuesday & Wednesday) – Houston, TX

October 6 & 7 (Tuesday & Wednesday) – Houston, TX

Visit our Seminars webpage for updates & registration information.

TRRC Risk-Based Leak Survey Program

16 TAC Chapter 8 – Pipeline Safety Regulations

As a reminder, The Texas Railroad Commission (TRRC) adopted new §8.206, “Risk-Based Leak Survey Program” effective September 1, 2008, for operators of gas distribution pipeline systems. The adopted rules require Texas gas distribution companies to establish a risk-based schedule of increased leak inspections; standardize leak grading and repair time frames (§8.207); and the mandatory removal and replacement program of leaks identified on compression couplings that join both steel and plastic pipe (§8.208). Please reference RCP's newsletter article on the proposed rule in the July 2008 edition of DOT Pipeline Compliance News.

Beginning November 1, 2008, and every six months thereafter until all compression couplings on the operator's system subject to §8.208(f) have been removed and replaced, each operator shall file with the division a progress report showing the number of service riser installations checked, the condition of the coupling, and the total number of compression couplings replaced for that reporting period.

For more information, or a copy of the new rule, contact Jessica Roger.

Leak Management Tracking System

RCP has developed a leak management system that tracks all leaks through their life span and will allow for the reports required by the TRRC to be easily generated and uploaded into the TRRC Electronic Document Interchange process. It is a web-based application that can be customized so that field personnel can interface through laptops or hand-held devices. Because it is web-based, there are no IT issues to struggle through to get started. Simple to use, easy to access, and can be customized with GIS integration tools, etc. For more information Click here to contact Jessica Roger.

Emergency Planning and Community Right-to-Know Act (EPCRA)

[Docket EPA-HQ-SFUND-1998-0002]

Sections 311 and 312 of EPCRA apply to any facility that is required to prepare or have available a Material Safety Data Sheet (MSDS) for any hazardous chemical under the Occupational Safety and Health Administration (OSHA) and its implementing regulations. Effective on December 3, 2008, EPA is finalizing changes to the Emergency Planning Notification, Emergency Release Notification and Hazardous Chemical Reporting regulations that were proposed on June 8, 1998. EPA proposed four major revisions and provided draft guidance on various reporting options that States and local agencies may wish to consider in implementing the hazardous chemical reporting requirements. This action addresses only those changes proposed under the heading "Other Regulatory Changes" described in the preamble to the 1998 proposed rule. This final action includes minor revisions to the Emergency Planning Notification, Emergency Release Notification and Hazardous Chemical Reporting regulations, codifying statutory requirements, and clarifying certain interpretations and policy statements that EPA has provided to the regulated community. This final action does not affect public access to any of the information provided under the Emergency Planning Notification, Emergency Release Notification and Hazardous Chemical Reporting regulations. In addition to the regulatory changes, the Agency is finalizing the plain language format of the regulations. Each section in these regulations will be re-numbered and tables will be added for further clarification. Improving the clarity of the regulatory requirements will make the rule easier to understand and improve compliance.

For additional information or for a copy of the applicable federal register notice, please contact Jessica Roger.

Interested in Web-Based Compliance Management Systems?

RCP has the latest technology to help manage all of your permits, inspections, procedures, and data requirements and neatly organize them into one overall compliance assurance system. Because it is web-based, there are no IT issues to struggle through to get started. For more information, click here to contact Jessica Roger.

Update of Bureau of Land Management Linear Right-of-Way Rent Schedule

Effective December 1, 2008, the Bureau of Land Management (BLM) is amending its right-of-way regulations to update the linear right-of-way rent schedule in 43 CFR parts 2800 and 2880. The rent schedule covers most linear rights-of-way granted under Title V of the Federal Land Policy and Management Act of 1976, as amended (FLPMA), and Section 28 of the Mineral Leasing Act of 1920, as amended (MLA). Those laws require the holder of a right-of-way grant to pay annually, in advance, the fair market value to occupy, use, or traverse public lands for facilities such as power lines, fiber optic lines, pipelines, roads, and ditches.

Section 367 of the Energy Policy Act of 2005 (the Act) directs the Secretary of the Interior to update the per acre rent schedule found in 43 CFR 2806.20. The Act requires that the BLM revise the per acre rental fee zone value schedule by state, county, and type of linear right-of-way use to reflect current land values in each zone. The Act also requires the Secretary of Agriculture (Forest Service) to make the same revisions for rights-of-way on National Forest System (NFS) lands. This final rule:

  • Makes clear that the rent exemptions listed in section 2806.14 do not apply if the applicant/holder is in trespass;
  • Provides that only the Per Acre Rent Schedule will be used to determine rent for linear right-of-way grants, unless the land encumbered by the grant is to be transferred out of Federal ownership;
  • Provides for an annual rent payment term when the annual rent for non-individuals is $500 or more;
  • Provides for a one-time rent payment for grants and easements when the land encumbered by the grant or easement is to be transferred out of Federal ownership;
  • Provides for a limited phase-in provision to all holders for calendar year 2009, and, a possible additional phase-in period upon revision of the rent schedule under sections 2806.22(b) and 2885.19(a);
  • Revises section 2920.6 to require reimbursement of processing and monitoring costs under sections 2804.14 and 2805.16 for applications for leases and permits issued under Title III of FLPMA;
  • Amends section 2920.8(b) to assess a non-refundable processing fee and monitoring fee under sections 2804.14 and 2805.16 for each request for renewal, transfer, or assignment of a lease or easement;
  • Amends sections 2805.11(b)(2) and 2885.11(a) so that all grants, except those issued for a term of 3 years or less and those issued in perpetuity under ‡FLPMA, expire on December 31 of the final year of the grant; and
  • Amends sections 2805.14(f) and 2885.12(e) to make it clear that you may assign your grant, without the BLM's prior written approval, if your authorization so provides.

For information on the substance of the final rule, please contact Bil Weigand at (208) 373-3862 or Rick Stamm at (202) 452-5185. For information on procedural matters, please contact Ian Senio at (202) 452-5049.

Technical Advisory Committee Meeting Notice

[Docket No. PHMSA-RSPA-1998-4470]

The Technical Pipeline Safety Standards Committee (TPSSC) and the Technical Hazardous Liquid Pipeline Safety Standards Committee (THLPSSC) will meet in Arlington, VA on December 11 and 12 to discuss two important regulatory proposals and several future regulatory initiatives.

  • The TPSSC and the THLPSSC will meet jointly on Thursday, December 11 from 9 a.m. to 5 p.m., to discuss and vote on the proposed rule on Control Room Management/Human Factors. (Please reference RCP's newsletter article on the proposed rule in the October 2008 edition of DOT Pipeline Compliance News.)
  • The TPSSC will meet on Friday, December 12 from 9 a.m. to 5 p.m. EST to discuss and vote on the proposed rule for Integrity Management Program for Gas Distribution Pipelines. (Please reference RCP's newsletter article on the proposed rule in the July 2008 edition of DOT Pipeline Compliance News.)

The meetings will take place at the Westin Arlington Gateway, 801 North Glebe Road, Arlington, VA 22203. The phone numbers for reservation are 1-888-627-7076 or (703) 717-6200. Rooms are reserved at the hotel under USDOT Technical Advisory Committee meetings. For a guaranteed room at the hotel, attendees need to make their reservations no later than November 10, 2008. Priority is given to Committee members and to State Pipeline Safety Representatives.

Name badge pick-up and on-site registration will be available on December 11 starting at 8 a.m. with the agenda taking place from 9 a.m. until approximately 5 p.m. Refer to the meetings web site for updated agenda and times at: http://primis.phmsa.dot.gov/meetings/Mtg56.mtg. Please note that the meetings will not be Web casted. However, presentations will be available on the meetings website within 30 days following the meetings.

Technical Assistance Grants to Communities

[Docket ID PHMSA-2008-0292]

PHMSA has established the criteria and competitive procedures that will be used in awarding grants under the Technical Assistance Grants (TAG) program authorized in 49 U.S.C. 60130 and section 2(e) of the Pipeline Inspection, Protection, Enforcement, and Safety Act of 2006. Subject to future appropriations, the TAG program will provide grants of up to $50,000 each to local governments and community groups for engineering and other technical assistance related to pipeline safety matters.

PHMSA has also announced their plans for awarding the three demonstration grants authorized under the TAG program. These demonstration grants (not exceeding $25,000 each) are expected to assist pilot communities with testing draft recommended practices currently being developed by the Pipelines and Informed Planning Alliance (PIPA) task teams. PHMSA, in consultation with the PIPA Steering Committee, will select the three pilot communities based on the Applicant's interest in pilot testing draft PIPA best practices. Each demonstration grant recipient will be required to provide a report to PHMSA demonstrating completion of the work as outlined in the grant agreement. Further, each recipient of a grant under section 5 must ensure that:

  • The technical findings made possible by the grants are made available to the relevant operators; and
  • Open communication is maintained between the grant recipients, local operators, local communities and other interested parties.

PHMSA and the PIPA Steering Committee have identified several potential projects and topics they may ask communities to investigate, including: Performing an annual review with pipeline operators having facilities within the community; mapping pipelines, abandoned pipelines and Consultation Zones in a geographic information system (GIS); drafting a model ordinance and reviewing one or more of the proposed PIPA best practices for legal issues associated with incorporating the best practices into law; developing educational material for local governments to distribute to developers, landowners and operators about Consultation Zones; or performing Consultation Zone discussions for several developments now being planned that are in close proximity to a transmission pipeline.

FOR FURTHER INFORMATION CONTACT: Steven Fischer by e-mail at steve.fischer@dot.gov.

Ongoing Resources

These articles are maintained and updated as new information becomes available.

Last Updated: October 2026

Regulatory Watch: Key Dates & Deadlines

Welcome to Regulatory Watch! In this monthly update, we’ll keep you informed on proposed rule comment periods, effective dates, and upcoming deadlines for various compliance requirements.

Proposed Rule Stage

2137-AF37Proposed Rule Stage

Oil Spill Response Plans, Accident Notifications, Inspections and Investigations and other Miscellaneous Pipeline Safety Changes

2137-AF52Proposed Rule Stage

Pipeline Operational Status

2137-AF60Proposed Rule Stage

Safety of Carbon Dioxide and Hazardous Liquid Pipelines

Final Rule Stage

2137-AF53Final Rule Stage

Safety of Gas Distribution Pipelines and Other Pipeline Safety Initiatives

Sprint I & II Update

To further the Administration’s deregulatory policies, PHMSA has published in today’s Federal Register twenty-eight (28) separate rulemaking actions affecting the pipeline safety regulations (PSR; Parts 190-199). Click here to access the documents.

Rulemaking Description Stage Code
Pipeline Safety: Rationalize Special Permit Conditions PHMSA proposes to amend its special permit procedures to ensure permit conditions are directly tied to the specific pipeline safety regulations being waived. NPRM 49 CFR Part 190
Pipeline Safety: Rationalize Calculation of Regulatory Filing and Compliance Deadlines PHMSA will clarify that regulatory filing and compliance deadlines falling on weekends or Federal holidays automatically move to the next business day. DFR 49 CFR Part 190
Pipeline Safety: Adjust Annual Report Filing Timelines PHMSA will amend annual reporting requirements to move the gas pipeline annual report submission deadline from March to June. DFR 49 CFR Part 191
Pipeline Safety: Property Damage Definition for Incident Reporting PHMSA will clarify incident reporting property damage calculations for gas pipelines and update hazardous liquid accident reporting thresholds using inflation-adjusted criteria. DFR 49 CFR Parts 191 & 195
Pipeline Safety: Exception for In-Plant Piping Systems PHMSA proposes to clarify that in-plant piping systems are not subject to federal pipeline safety regulations. NPRM 49 CFR Part 192
Pipeline Safety: Codify Enforcement Discretion on Incidental Gathering Lines PHMSA proposes to codify enforcement discretion clarifying that restrictions on the historical incidental gathering line exemption apply only to newly constructed lines. NPRM 49 CFR Part 192
Pipeline Safety: Eliminate Burdensome Coating Assessment Deadlines PHMSA proposes to replace prescriptive deadlines for coating damage assessments and remediation with a requirement that activities be completed before the pipeline is placed in service. NPRM 49 CFR Part 192
Pipeline Safety: Atmospheric Corrosion Reassessment for Pipeline Replacements PHMSA proposes to remove the 3-year reassessment interval following replacement of atmospheric corrosion defects and allow use of the standard 5-year reassessment interval. NPRM 49 CFR Part 192
Pipeline Safety: Harmonize Class Change Pressure Test Requirements PHMSA proposes to reduce the minimum pressure test duration following certain class location changes from 8 hours to 4 hours, aligning with existing Subpart J requirements. NPRM 49 CFR Part 192
Pipeline Safety: Clarify MAOP Reconfirmation Testing Records PHMSA will issue a technical correction clarifying that operators may use pre-1970s pressure test records when reconfirming MAOP under §192.624. Final Rule 49 CFR Part 192
Pipeline Safety: Remote Sensing Technologies for ROW Patrols PHMSA will explicitly allow right-of-way patrols to be conducted using unmanned aircraft systems, satellites, and other remote sensing technologies. DFR 49 CFR Parts 192 & 195
Pipeline Safety: Technical Standards Updates and Amendments PHMSA will update incorporated standards and make technical amendments in response to an industry petition for reconsideration. Final Rule 49 CFR Part 192
Pipeline Safety Program: Update of Standards Incorporated by Reference PHMSA issued multiple direct final rules updating incorporated industry consensus standards used throughout Parts 192 and 195, replacing outdated editions with current versions. Multiple DFRs 49 CFR Parts 192 & 195

The following is a summary of the 40 rulemakings that PHMSA published in the Federal Register on April 24, 2026. If any adverse comment is received to a DFR PHMSA must rescind the rule and repropose. Click here to access the documents.

Rulemaking Description Stage Code
Pipeline Safety and Hazardous Materials Safety: Amendments to PHMSA Procedural Regulations PHMSA proposed miscellaneous amendments to procedural regulations governing informal rulemaking for both pipeline safety and hazardous materials programs. NPRM 49 CFR Part 190
Pipeline Safety: Interpretation Request Procedures PHMSA amended interpretation procedures to require publication of interpretation requests on its website and provide an opportunity for public comment. Final Rule 49 CFR Part 190
Pipeline Safety: Declaratory Order Procedures PHMSA established formal procedures for issuing declaratory orders through a new section in Part 190. Final Rule 49 CFR Part 190
Pipeline Safety: Consent Orders PHMSA clarified that consent agreements may be used to resolve enforcement actions, including cases involving civil penalties. Final Rule 49 CFR Part 190
Pipeline Safety: Adjustment to OPID Notifications for Construction PHMSA proposed adjusting the inflation-based threshold that triggers OPID notifications for certain construction and facility modification activities. NPRM 49 CFR Part 191
Pipeline Safety: Eliminating Limitations on Welders and Welding Operators PHMSA proposed allowing welders qualified through non-destructive testing methods to perform compressor station welding activities currently subject to additional restrictions. NPRM 49 CFR Part 192
Pipeline Safety: Material Properties Verification During MAOP Reconfirmation PHMSA proposed clarifying that material testing at pressure test manifold sites is not required when traceable, verifiable, and complete material records already exist. NPRM 49 CFR Part 192
Pipeline Safety: Electronic Retention of Part 194 Response Plans PHMSA amended regulations to allow operators to maintain electronic copies of response plans instead of paper copies. DFR 49 CFR Part 194
Pipeline Safety: Remote Monitoring of Rectifiers PHMSA proposed allowing remote monitoring technologies for rectifiers used in external corrosion control programs. NPRM 49 CFR Part 195
Pipeline Safety: Clarifying Hazardous Liquid High-Consequence Area Designations PHMSA amended HCA guidance to clarify spill considerations in agricultural fields and reorganize threat identification guidance. DFR 49 CFR Part 195
Pipeline Safety: Timeframe to Make Rupture-Mitigation Valves Operational PHMSA proposed extending the deadline for placing rupture-mitigation valves into operation from 14 days to 90 days after a pipeline enters service. NPRM 49 CFR Part 192
Pipeline Safety: Hazardous Liquid Valve Maintenance Schedule PHMSA proposed allowing operators to implement risk-based valve maintenance schedules, subject to a maximum inspection interval of one year. NPRM 49 CFR Part 195
Pipeline Safety: Property Damage Definition for Incident Reporting PHMSA proposes revising property damage thresholds for reportable gas and hazardous liquid pipeline incidents and clarifying applicability to telephonic notifications. NPRM 49 CFR Parts 192 & 195
Pipeline Safety: Remote Sensing Technologies for ROW Patrols PHMSA proposes clarifying that unmanned aerial systems, satellites, and other remote-sensing technologies may be used to satisfy right-of-way patrol requirements. NPRM 49 CFR Parts 192 & 195
Pipeline Safety: Adjust Annual Report and NPMS Filing Timelines PHMSA proposes extending annual report and NPMS submission deadlines for gas pipeline and storage operators to June 15 each year. NPRM 49 CFR Part 191
Pipeline Safety: Editorial Corrections and Clarifications PHMSA issued multiple final rules correcting editorial errors, updating references, removing obsolete submission methods, and improving regulatory clarity. Final Rules Various
Pipeline Safety: Update of Standards Incorporated by Reference PHMSA issued multiple direct final rules updating incorporated industry consensus standards, including NFPA, ASTM, MSS, NACE, and ASME standards. Multiple DFRs 49 CFR Parts 192 & 195

Have questions about an upcoming deadline? Please reach out to Jessica Foley for assistance!

Last Updated: October 2026

Conference News

Jan252027

Pipeline Pigging and Integrity Management Conference

▦ January 25, 2027 – January 28, 2027⌖ George R. Brown Convention Center, Houston, TX

The 39th International Pipeline Pigging & Integrity Management Conference (PPIM) will take place at the George R. Brown Convention Center in Houston. The event brings together pipeline operators, engineers, and industry professionals to explore advancements in pipeline inspection, integrity management, risk assessment, and emerging technologies.…

ExhibitingBooth 524
RCP Team Attending
Heather RoarkHeather RoarkSales & Marketing Coordinator
Jessica FoleyJessica FoleyVice President
Featured Presentations
Chris McLaren
Chris McLarenExecutive Consultant
October 27, 2026 at 7:30 AM
Event Details
Last Updated: October 2026

PSI Training Schedule

Date Training Course Price Registration
Nov 17 – Nov 19, 2026 DOT Pipeline Compliance Workshop $2,150 SOLD OUT
Feb 16 – Feb 18, 2027 Pipeline Safety Audit Training $2,150 Register →
Feb 23 – Feb 25, 2027 Advanced Pipeline Risk Assessment Workshop $2,150 Register →
Mar 23 – Mar 25, 2027 DOT Pipeline Compliance Workshop $2,150 Register →

WEBINAR RECORDING!
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition

RCP and the Pipeline Safety Institute offered a free webinar exploring the 2nd Editions of API RP 1170, Design and Operation of Solution-mined Salt Caverns Used for Natural Gas Storage and API RP 1171, Functional Integrity of Natural Gas Storage in Depleted Hydrocarbon Reservoirs and Aquifer Reservoirs. Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!

WEBINAR RECORDING
Pipeline Safety: Unpacking the Class Location Change Requirements

Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!

You asked and we listened!

Advanced DOT Pipeline Compliance Workshop is on the calendar!

This intensive and interactive 3-day, in-person workshop is designed for those who have previously completed our DOT Pipeline Compliance Workshop and are ready to take their knowledge to the next level.

New Workshop Alert!

Prepare Your Team for Pipeline Safety Audits with Confidence!

Our 3-day Pipeline Safety Audit Workshop is tailored for professionals responsible for the safe operation of hazardous liquid and natural gas pipelines. Designed for groups of 10-15 participants, this interactive training…

On-Site Training Request

We have conducted on-site training for oil and gas companies for over 25 years and can provide customized workshops for companies with groups of five or more.

We would welcome the opportunity to discuss our services with you.

Sincerely,

W. R. (Bill) Byrd, PE
President
RCP Inc.