DOT Drug and Alcohol Testing Programs; Technical Amendments; Response to Comments

On August 9, 2001, the Department of Transportation made a series of technical amendments to its drug and alcohol testing procedural rule, which go into effect August 1, 2001. The purpose of these technical amendments is to clarify certain provisions of the rule and address omissions or problems which have been called to the DOT's attention since the publication of the final rule in December 2000. This includes multiple changes and clarifications to definitions (e.g. what is an "invalid drug test"), and other guidance (e.g. can an employer require an employee to sign a consent or release), etc.

Also on August 9, the DOT responded to comments by maritime industry groups and others concerning the pre-employment inquiry provision of the Department-wide regulations on transportation workplace drug and alcohol testing procedures (Part 40 rule). They also published a "common preamble" discussing issues raised with respect to the Part 40 rule in comments to DOT agency proposals to amend their drug and alcohol testing rules to conform to the Part 40 rule.

Both documents are available on RCP's website here, 66 FR 41944 8-9-01 Drug Testing Amendments.pdf, and 66 FR 41955 8-9-01 Drug Testing – other amendments.pdf.

Corps of Engineers – Nationwide Permit Revisions – Request for Comments

The Corps of Engineers is soliciting comments for the reissuance of the existing Nationwide Permits (NWPs), General Conditions, and definitions with some modifications. The Corps is proposing to modify NWPs 14, 21, 27, 31, 37, 39, 40, 42, and 43. In addition, they are proposing to modify General Conditions 4, 9, 13, 19, 21, 26, and add a new General Condition 27. In order to reduce the confusion regarding the expiration of the NWPs and the administrative burden, it is the Corps intent to reissue all NWPs and General Conditions contained within this Notice, including those not scheduled to expire on February 11, 2002. Thus, all issued, reissued and modified NWPs, and General Conditions contained within this notice will become effective and expire on the same date. The reissuance process starts with the publication of the proposed NWPs in the Federal Register and concurrent release of public notices by Corps District offices for a 45-day comment period. The Corps will review the comments received in response to this Federal Register notice and the public hearing with a task force that includes Corps Regulatory field personnel. This process will take approximately 60-days. Upon completion of the initial review of the comments, the Corps will complete a draft of the final NWPs and solicit comments from interested Federal agencies. The final version of the NWPs will be published in the Federal Register by November 13, 2001. The NWPs will then become effective by February 11, 2002.

FOR FURTHER INFORMATION CONTACT: Mr. Rich White or Mr. Sam Collinson, at (202) 761-4599 or access the U.S. Army Corps of Engineers Regulatory Home Page at: http//:www.usace.army.mil/inet/functions/cw/cecwo/reg/. Send comments to HQUSACE, ATTN: CECW-OR, 441 "G" Street, NW, Washington, DC 20314-1000 by September 24, 2001. The public hearing will be held at 1 p.m. on September 12, 2001 at the GAO Building, 441 "G" Street, NW, Washington, DC 20314-1000, 7th floor auditorium.

The entire notice can be downloaded from RCP's website HERE.

Upcoming RCP Seminars

RCP will conduct a 2 1/2 day workshop on DOT Pipeline Regulations on September 18th through 20th in Houston.

Day 1 includes an overview of the pipeline regulations in general, and is appropriate for people who are just getting involved in DOT pipeline regulations, and for management personnel who need to understand the basic issues and areas of coverage for these regulations.

Day 2 will provide an overview of proposed and recent regulatory initiatives such as operator qualification and pipeline integrity management. This day is appropriate for all personnel who need to understand these initiatives and who need to know about proposed rules that MAY impact their business in the future.

Day 3 provides a half day workshop dedicated to OPA-90 oil spill response planning for DOT pipelines, and is appropriate for all personnel who are responsible for or associated with oil spill response planning for pipelines. The early registration deadline is September 4. Additional information is available on our website HERE.

Pending Audits?

Has the DOT notified you of a pending audit? RCP can provide confidential internal auditing to help ensure that your facilities are up to the agency's latest standards.

Operator Qualification Rule – Minor Corrections

On August 20, 2001, the DOT made some minor corrections to the final regulations on qualification of pipeline personnel, which were published in the Federal Register on August 27, 1999 (64 FR 46853) (see RCP's September, 1999 DOT newsletter)HERE. These corrections are minor and do not affect the substance or content of the rule. The changes apply to both the Gas and Liquid regulations, and are effective immediately.

The revisions add the title, "Qualification of Pipeline Personnel", to subpart N of 49 CFR 192 and to subpart G of 49 CFR 195. In addition, the final regulations contained incorrect numbering for the evaluation methods in §192.803(b) and §195.503(b). The correct numbering is:

Evaluation means a process, established and documented by the operator, to determine an individual's ability to perform a covered task by any of the following:

(a) Written examination; (b) Oral examination; (c) Work performance history review; (d) Observation during: (1) Performance on the job, (2) On the job training, or (3) Simulations; (e) Other forms of assessment.

NOTE: the original rule numbered all these items sequentially (a) through (h), with no subparts (1), (2), and (3) under (d).

Lastly, the cutoff date for the use of experience under the Work Performance History Review option was extended by 2 months, and now reads:

Work performance history review may be used as a sole evaluation method for individuals who were performing a covered task prior to October 26, 1999.

Note: the original rule cutoff date was August 27, 1999.

Acquiring a pipeline?

RCP can provide due diligence audits to help you ensure that potential compliance issues have been addressed before the sale is final.

Risk Management Demonstration Program – Natural Gas Pipeline Company of America (NGPL) project

NGPL, a company previously selected to participate in the Risk Management Demonstration Program, has identified five pipeline segments in its system (all changing from Class 2 to Class 3) where it proposes to conduct risk control alternatives to the class location change requirements in 49 CFR §192.611. OPS seeks public comment on the proposed demonstration project modification so that it may consider and address these comments before modifying the order to approve the proposed risk control alternatives (the "Alternatives"). OPS requests that comments to this Notice or about this environmental assessment be submitted on or before September 17, 2001 so they can be considered before the modifications are approved. However, comments on this or any other demonstration project will be accepted in the Docket throughout the demonstration period (docket number RSPA-98-4034).

NGPL identified outside force damage and corrosion as the principal risks to the pipeline in the class location segments and the surrounding sections and defined the following risk control alternatives to achieve superior safety and environmental protection along these five segments:

  • Internally inspecting class location change segments (and an extended length of pipe bordering each class change segment) using geometry and magnetic flux leakage in-line inspection tools, and repairing indications of corrosion or existing construction and outside force damage identified by the internal inspection.
  • Performing close-interval surveys on the five class location segments and an extended length of pipe bordering each class location segment.
  • Pressure testing the five class location change segments, an extended length of pipe that encompasses each class location segment, and additional segments on the same pipelines.
  • Enhancing damage prevention activities in the class location change segments and an additional length of pipe bordering each class location segment.
  • Increasing contacts with local emergency planners and emergency responders to ensure preparation for more effective and coordinated response to emergencies.
  • Conducting public education on the subject of pipeline safety; part of this education program will be specifically developed for students in schools in the immediate vicinity of the Gulf Coast line class location segments.
  • Continuing the NGPL current investigation, analysis, and mitigation program for Stress Corrosion Cracking (SCC). This company program, initiated in response to recent experience on the NGPL system, involves integration of data regarding soil, coating, and pipe characteristics to identify areas of probable susceptibility to SCC. These areas are then investigated further to determine if SCC is present; any detected SCC is mitigated.

As part of the company's risk evaluation, NGPL has compared the risk reduction produced by these alternatives to that achieved by the current regulations. OPS has reviewed this evaluation in detail and concluded that the alternative risk control activities can be expected to reduce safety and environmental risk below that which would be achieved by compliance with 49 CFR 192.611. Furthermore, because of the resources saved by not having to replace pipe in these five locations, NGPL is able to conduct internal inspections and pressure tests on additional portions of its system.

Pipeline Safety: Meeting of Gas Pipeline Safety Advisory Committee

The Technical Pipeline Safety Standards Committee (TPSSC) will meet on Thursday, September 13, 2001 from 9 a.m. to 5 p.m. Members of the public may attend the meeting in person at Dulles Airport Marriott, 45020 Aviation Drive, Dulles, VA 20166; phone (703) 471-9500. Due to limited space, anyone wishing to attend or participate should notify Juan Carlos Martinez, at (202) 366-1933, not later than August 30, 2001.

The TPSSC is a statutorily mandated advisory committee that advises RSPA on proposed safety standards for gas pipelines. The committee consists of 15 members-five each representing government, industry, and the public. On July 27, 2001, RSPA issued a notice of request for comments, "Pipeline Safety: Integrity Management in High Consequence Areas (Gas Transmission Pipelines)," (66 FR 34318, docket number RSPA 00-7666 ). RSPA sought further information and clarification, and invited further public comment about integrity management concepts as they relate to gas pipelines. To prepare the TPSSC for future consideration of proposed rules on integrity management programs for gas pipelines, RSPA will brief the Committee on integrity management concepts for gas pipelines and on the comments received in response to the notice.

Discussions will be focused on a summary of comments on the seven elements described in the notice:

  1. Defining high consequence areas.
  2. Identifying and evaluating threats to pipeline integrity.
  3. Selecting the assessment technologies.
  4. Determining time frames to conduct a baseline integrity assessment and to make repairs.
  5. Identifying and implementing additional preventive and mitigative measures.
  6. Continually evaluating and reassessing pipeline segments.
  7. Monitoring the effectiveness of the management process.

In addition, the TPSSC will be briefed on the progress of the American Society of Mechanical Engineers' B31.8 Committee on the Integrity Management Standard. This new standard will outline the technical guidance for implementation of an operator's integrity management plan, including data management, quality control, management of change and communication.

FOR FURTHER INFORMATION CONTACT: Cheryl Whetsel, OPS, (202) 366-4431 or Richard Huriaux, OPS, (202) 366-4565, regarding the subject matter of this notice.

Natural Resource Damage Assessments – Proposed Rule Revisions

On July 30, 2001, the National Oceanic and Atmospheric Administration (NOAA) proposed amendments to their Natural Resource Damage Assessment rule in 15 CFR 990. The proposal addresses issues from a recent court ruling, and includes some clarifying and technical amendments in other parts of the regulation. This rule will affect companies that are held responsible for natural resource damages for oil and other hazardous substance spills, including liquid pipeline operators and dock operators. The entire notice can be downloaded from RCP's website HERE.

In the event of a discharge or substantial threat of a discharge of oil (incident), the Oil Pollution Act of 1990 (OPA-90), provides that federal, state, Indian tribal, and/or foreign natural resource trustees assess natural resource damages and develop and implement a plan for the restoration, rehabilitation, replacement, or acquisition of the equivalent, of the injured natural resources and their services under their trusteeship. Congress directed the National Oceanic and Atmospheric Administration (NOAA) to promulgate regulations for the assessment of natural resource damages resulting from an incident (OPA section 1006(e)(1)). NOAA promulgated final regulations on January 5, 1996 (see 61 FR 440), codified at 15 CFR Part 990.

Under these OPA regulations, trustees conduct natural resource damage assessments in the open, with responsible parties and the public involved in the planning process to achieve restoration more quickly, decrease transaction costs, and avoid litigation. These restoration plans form the basis of claims for natural resource damages. Under the natural resource damage assessment regulation, trustees then present a demand comprised of the final restoration plan to responsible parties for funding or implementation.

MMS Proposed Rule for Pipeline Repairs on the OCS

The Minerals Management Service (MMS) in the Department of the Interior (DOI) is authorized to issue and enforce rules to promote safe operations, environmental protection, and resource conservation on the Outer Continental Shelf (OCS). Under this authority, MMS regulates pipeline transportation of mineral production and rights-of-way for pipelines and associated facilities. MMS approves all OCS pipeline applications, regardless of whether a pipeline is built and operated under DOI or Department of Transportation (DOT) regulatory requirements. MMS also has sole authority to grant rights-of-way for OCS pipelines.

EDITORS NOTE to DOT Pipeline Operators in the Gulf of Mexico – this rule will apply to you!

The proposed rule pertains to any pipeline modification or repair that involves cutting into a pipeline or opening a pipeline at a flange. It requires that all lessees, lease operators, and pipeline right-of-way holders submit in writing the measures they plan to take and the procedures they plan to follow to ensure the safety of offshore workers and to prevent pollution before beginning any repair. For example:

Each lessee, lessee's operator, or pipeline right-of-way holder would be required, for any pipeline modification or repair that involves either cutting into a pipeline or opening a pipeline at a flange, to provide to the MMS Regional Supervisor a written work plan with their application to do the work that addresses the specific measures they plan to take and the procedures they plan to follow to ensure the safety of offshore personnel and to prevent pollution. The lessee, lease operator, or pipeline right-of-way holder-must submit and obtain the Regional Supervisor's approval for an application before they may conduct any of the following operations:

(1) Install a pipeline;

(2) Modify a pipeline;

(3) Cut into a pipeline or open a pipeline at a flange for purposes of modifying or repairing a

pipeline; or

(4) Decommission a pipeline.

If you submit an application for a pipeline modification or repair that involves cutting into a pipeline or opening a pipeline at a flange, you must include a written work plan with your application. Your written work plan must include a description of the specific measures you intend to take and the procedures you plan to follow to ensure the safety of offshore workers and to prevent pollution during the modification or repair. If you intend to repair a pipeline by installing a full encirclement mechanical clamp on the pipeline and do not intend to either cut into or open the pipeline at a flange, you do not have to submit a written work plan with your application. In writing a work plan, you must:

(1) Consider the operating history of the pipeline segment you plan to modify or repair, including past modifications or repairs and operating conditions peculiar to the pipeline segment;

(2) Develop all reasonable measures to ensure that pressure in the pipeline segment is equal to the external pressure (internally, there should be neither over-pressure nor negative pressure relative to external pressure);

(3) Develop all reasonable measures to ensure that you purge all combustibles and hydrogen sulfide (H²S) from the pipeline segment immediately before you conduct any work;

(4) Develop procedures to inform all facility workers (both company and contract) in advance concerning significant aspects of the modification or repair;

(5) Develop procedures to alert all facility workers immediately before you attempt to de-pressurize the pipeline and immediately before you cut into or open the pipeline to perform the modification or repair;

(6) Maintain onsite supervision during the entire modification or repair; and

(7) Develop procedures and safeguards to ensure that the pipeline segment remains isolated during the entire modification or repair so that facility workers (both company and contract) are not endangered by pressure differentials, H²S, or combustibles.

You must notify the Regional Supervisor within 24 hours after you decide that a pipeline repair is necessary, or immediately in cases of a pipeline failure. All such notifications must be made before you start the repair work. You must also submit a confirmation report of the repair of any pipeline or pipeline component to the Regional Supervisor within 30 days after you complete the work. Your confirmation report must include the following:

(1) Description of the repair;

(2) X-Y coordinates of the pipeline repair;

(3) Confirmation of the damage to or failure of the pipeline as originally reported;

(4) Confirmation that the repair was completed as approved by the Regional Supervisor; and

(5) Results of the hydrostatic pressure test.

MMS will consider all comments received by October 29, 2001. The complete proposed rule can be accessed on RCP's website HERE.

OPS PIM Workshop

Quick-Hit coming your way? One item of interest from the OPS Integrity Management meeting in Houston on August 7 and 8 was the inspection process for integrity management programs. OPS intends to do "quick hit" inspections of all affected operators in the first 4 months of 2002. During these inspections, OPS will:

  1. ensure that appropriate segments that could affect HCAs have been identified,
  2. ensure that baseline assessment plans and integrity management programs have all the essential elements,
  3. identify any noteworthy practices that should be shared with other pipeline operators, and
  4. prioritize operators for more in-depth inspections to be conducted later in 2002.

The presentation materials from this workshop are now available at http://www.cycla.com/opsiswc/wc.dll?webdoc~Details~&id;=001848&query;=no&prj;=0052⊂=11&lp;=62&u;=lp. The next workshop will be held on October 10 and 11, 2001 from 8:30 a.m. to 5:00 p.m., at the Renaissance Houston Hotel, 6 Greenway Plaza East, Houston, Texas, 77046, 713-629-1200 or 800-Hotels-1. Rooms may be reserved within a block identified as "DOT/IMP Public Meeting Block" no later than September 12, 2001. Please notify Beth Callsen if you’re planning to attend the October workshop at beth.callsen@rspa.dot.gov or at 202-366-4572.

PIM Nomenclature

One more item of interest from the OPS Integrity Management Workshop in Houston this month was the nomenclature that Kinder Morgan is using to describe pipeline segments that "are in or could effect" a High Consequence Area. We think they did a great service to the pipeline industry by defining 3 distinct areas, as follows, and expect that others in the pipeline industry will quickly adopt these definitions as useful and fairly self-explanatory:

  1. Direct Impact Zone: areas where a pipeline is physically located within an HCA.
  2. Indirect Impact Zone: areas where a pipeline is within a certain buffer distance from an HCA (the distance to be used will vary depending on the pipeline size / flowrate / etc.).
  3. Potential Transport Zone: areas outside the Direct and Indirect Impact Zones that could be impacted by a spill. These areas will depend on terrain, discharge volumes, product types, HCA sensitivities, etc.

PIM Notifications

The last item of interest (at least, the last one we will mention in this edition) concerns the notifications that operators may need to make to OPS during their PIM program. These include:

1. desire to use an "other" assessment technology.

2. inability to meet required pipeline repair schedule.

3. desire to reasses at greater than 5 year intervals.

OPS made it clear that they expected such notifications to contain full and detailed justifications for the proposed action, that they will verify the information contained in the notification during their inspection process, and that they will post all operator notifications on their website. They also stated that they intend to take enforcement action if a notice is late, incomplete, or technically inadequate.

SouthWest Regional Gas Association Meeting Handout

Our president made a presentation to the SouthWest Regional Gas Association meeting in Phoenix, Arizona this week on State Pipeline Agency Rulemakings and Initiatives. One handout from that presentation was a summary table showing each state pipeline safety agency and the program delegations that they have received (intra-state gas program, etc.). That handout has been posted on our www.DOTPipeline.org website HERE. We believe that information in that table is up to date, but please feel free to e-mail us with any changes or clarifications that you think are appropriate.

Help Wanted

Know someone with regulatory expertise who is interested in full or part time work? Our recruiting coordinator would be glad to get their resume! Have them sent to chandra@your-rcp.com, or FAX to 713-655-8083.

Ongoing Resources

These articles are maintained and updated as new information becomes available.

Last Updated: October 2026

Regulatory Watch: Key Dates & Deadlines

Welcome to Regulatory Watch! In this monthly update, we’ll keep you informed on proposed rule comment periods, effective dates, and upcoming deadlines for various compliance requirements.

Proposed Rule Stage

2137-AF37Proposed Rule Stage

Oil Spill Response Plans, Accident Notifications, Inspections and Investigations and other Miscellaneous Pipeline Safety Changes

2137-AF52Proposed Rule Stage

Pipeline Operational Status

2137-AF60Proposed Rule Stage

Safety of Carbon Dioxide and Hazardous Liquid Pipelines

Final Rule Stage

2137-AF53Final Rule Stage

Safety of Gas Distribution Pipelines and Other Pipeline Safety Initiatives

Sprint I & II Update

To further the Administration’s deregulatory policies, PHMSA has published in today’s Federal Register twenty-eight (28) separate rulemaking actions affecting the pipeline safety regulations (PSR; Parts 190-199). Click here to access the documents.

Rulemaking Description Stage Code
Pipeline Safety: Rationalize Special Permit Conditions PHMSA proposes to amend its special permit procedures to ensure permit conditions are directly tied to the specific pipeline safety regulations being waived. NPRM 49 CFR Part 190
Pipeline Safety: Rationalize Calculation of Regulatory Filing and Compliance Deadlines PHMSA will clarify that regulatory filing and compliance deadlines falling on weekends or Federal holidays automatically move to the next business day. DFR 49 CFR Part 190
Pipeline Safety: Adjust Annual Report Filing Timelines PHMSA will amend annual reporting requirements to move the gas pipeline annual report submission deadline from March to June. DFR 49 CFR Part 191
Pipeline Safety: Property Damage Definition for Incident Reporting PHMSA will clarify incident reporting property damage calculations for gas pipelines and update hazardous liquid accident reporting thresholds using inflation-adjusted criteria. DFR 49 CFR Parts 191 & 195
Pipeline Safety: Exception for In-Plant Piping Systems PHMSA proposes to clarify that in-plant piping systems are not subject to federal pipeline safety regulations. NPRM 49 CFR Part 192
Pipeline Safety: Codify Enforcement Discretion on Incidental Gathering Lines PHMSA proposes to codify enforcement discretion clarifying that restrictions on the historical incidental gathering line exemption apply only to newly constructed lines. NPRM 49 CFR Part 192
Pipeline Safety: Eliminate Burdensome Coating Assessment Deadlines PHMSA proposes to replace prescriptive deadlines for coating damage assessments and remediation with a requirement that activities be completed before the pipeline is placed in service. NPRM 49 CFR Part 192
Pipeline Safety: Atmospheric Corrosion Reassessment for Pipeline Replacements PHMSA proposes to remove the 3-year reassessment interval following replacement of atmospheric corrosion defects and allow use of the standard 5-year reassessment interval. NPRM 49 CFR Part 192
Pipeline Safety: Harmonize Class Change Pressure Test Requirements PHMSA proposes to reduce the minimum pressure test duration following certain class location changes from 8 hours to 4 hours, aligning with existing Subpart J requirements. NPRM 49 CFR Part 192
Pipeline Safety: Clarify MAOP Reconfirmation Testing Records PHMSA will issue a technical correction clarifying that operators may use pre-1970s pressure test records when reconfirming MAOP under §192.624. Final Rule 49 CFR Part 192
Pipeline Safety: Remote Sensing Technologies for ROW Patrols PHMSA will explicitly allow right-of-way patrols to be conducted using unmanned aircraft systems, satellites, and other remote sensing technologies. DFR 49 CFR Parts 192 & 195
Pipeline Safety: Technical Standards Updates and Amendments PHMSA will update incorporated standards and make technical amendments in response to an industry petition for reconsideration. Final Rule 49 CFR Part 192
Pipeline Safety Program: Update of Standards Incorporated by Reference PHMSA issued multiple direct final rules updating incorporated industry consensus standards used throughout Parts 192 and 195, replacing outdated editions with current versions. Multiple DFRs 49 CFR Parts 192 & 195

The following is a summary of the 40 rulemakings that PHMSA published in the Federal Register on April 24, 2026. If any adverse comment is received to a DFR PHMSA must rescind the rule and repropose. Click here to access the documents.

Rulemaking Description Stage Code
Pipeline Safety and Hazardous Materials Safety: Amendments to PHMSA Procedural Regulations PHMSA proposed miscellaneous amendments to procedural regulations governing informal rulemaking for both pipeline safety and hazardous materials programs. NPRM 49 CFR Part 190
Pipeline Safety: Interpretation Request Procedures PHMSA amended interpretation procedures to require publication of interpretation requests on its website and provide an opportunity for public comment. Final Rule 49 CFR Part 190
Pipeline Safety: Declaratory Order Procedures PHMSA established formal procedures for issuing declaratory orders through a new section in Part 190. Final Rule 49 CFR Part 190
Pipeline Safety: Consent Orders PHMSA clarified that consent agreements may be used to resolve enforcement actions, including cases involving civil penalties. Final Rule 49 CFR Part 190
Pipeline Safety: Adjustment to OPID Notifications for Construction PHMSA proposed adjusting the inflation-based threshold that triggers OPID notifications for certain construction and facility modification activities. NPRM 49 CFR Part 191
Pipeline Safety: Eliminating Limitations on Welders and Welding Operators PHMSA proposed allowing welders qualified through non-destructive testing methods to perform compressor station welding activities currently subject to additional restrictions. NPRM 49 CFR Part 192
Pipeline Safety: Material Properties Verification During MAOP Reconfirmation PHMSA proposed clarifying that material testing at pressure test manifold sites is not required when traceable, verifiable, and complete material records already exist. NPRM 49 CFR Part 192
Pipeline Safety: Electronic Retention of Part 194 Response Plans PHMSA amended regulations to allow operators to maintain electronic copies of response plans instead of paper copies. DFR 49 CFR Part 194
Pipeline Safety: Remote Monitoring of Rectifiers PHMSA proposed allowing remote monitoring technologies for rectifiers used in external corrosion control programs. NPRM 49 CFR Part 195
Pipeline Safety: Clarifying Hazardous Liquid High-Consequence Area Designations PHMSA amended HCA guidance to clarify spill considerations in agricultural fields and reorganize threat identification guidance. DFR 49 CFR Part 195
Pipeline Safety: Timeframe to Make Rupture-Mitigation Valves Operational PHMSA proposed extending the deadline for placing rupture-mitigation valves into operation from 14 days to 90 days after a pipeline enters service. NPRM 49 CFR Part 192
Pipeline Safety: Hazardous Liquid Valve Maintenance Schedule PHMSA proposed allowing operators to implement risk-based valve maintenance schedules, subject to a maximum inspection interval of one year. NPRM 49 CFR Part 195
Pipeline Safety: Property Damage Definition for Incident Reporting PHMSA proposes revising property damage thresholds for reportable gas and hazardous liquid pipeline incidents and clarifying applicability to telephonic notifications. NPRM 49 CFR Parts 192 & 195
Pipeline Safety: Remote Sensing Technologies for ROW Patrols PHMSA proposes clarifying that unmanned aerial systems, satellites, and other remote-sensing technologies may be used to satisfy right-of-way patrol requirements. NPRM 49 CFR Parts 192 & 195
Pipeline Safety: Adjust Annual Report and NPMS Filing Timelines PHMSA proposes extending annual report and NPMS submission deadlines for gas pipeline and storage operators to June 15 each year. NPRM 49 CFR Part 191
Pipeline Safety: Editorial Corrections and Clarifications PHMSA issued multiple final rules correcting editorial errors, updating references, removing obsolete submission methods, and improving regulatory clarity. Final Rules Various
Pipeline Safety: Update of Standards Incorporated by Reference PHMSA issued multiple direct final rules updating incorporated industry consensus standards, including NFPA, ASTM, MSS, NACE, and ASME standards. Multiple DFRs 49 CFR Parts 192 & 195

Have questions about an upcoming deadline? Please reach out to Jessica Foley for assistance!

Last Updated: October 2026

Conference News

Jan252027

Pipeline Pigging and Integrity Management Conference

▦ January 25, 2027 – January 28, 2027⌖ George R. Brown Convention Center, Houston, TX

The 39th International Pipeline Pigging & Integrity Management Conference (PPIM) will take place at the George R. Brown Convention Center in Houston. The event brings together pipeline operators, engineers, and industry professionals to explore advancements in pipeline inspection, integrity management, risk assessment, and emerging technologies.…

ExhibitingBooth 524
RCP Team Attending
Heather RoarkHeather RoarkSales & Marketing Coordinator
Jessica FoleyJessica FoleyVice President
Featured Presentations
Chris McLaren
Chris McLarenExecutive Consultant
October 27, 2026 at 7:30 AM
Event Details
Last Updated: October 2026

PSI Training Schedule

Date Training Course Price Registration
Nov 17 – Nov 19, 2026 DOT Pipeline Compliance Workshop $2,150 SOLD OUT
Feb 16 – Feb 18, 2027 Pipeline Safety Audit Training $2,150 Register →
Feb 23 – Feb 25, 2027 Advanced Pipeline Risk Assessment Workshop $2,150 Register →
Mar 23 – Mar 25, 2027 DOT Pipeline Compliance Workshop $2,150 Register →

WEBINAR RECORDING!
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition

RCP and the Pipeline Safety Institute offered a free webinar exploring the 2nd Editions of API RP 1170, Design and Operation of Solution-mined Salt Caverns Used for Natural Gas Storage and API RP 1171, Functional Integrity of Natural Gas Storage in Depleted Hydrocarbon Reservoirs and Aquifer Reservoirs. Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!

WEBINAR RECORDING
Pipeline Safety: Unpacking the Class Location Change Requirements

Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!

You asked and we listened!

Advanced DOT Pipeline Compliance Workshop is on the calendar!

This intensive and interactive 3-day, in-person workshop is designed for those who have previously completed our DOT Pipeline Compliance Workshop and are ready to take their knowledge to the next level.

New Workshop Alert!

Prepare Your Team for Pipeline Safety Audits with Confidence!

Our 3-day Pipeline Safety Audit Workshop is tailored for professionals responsible for the safe operation of hazardous liquid and natural gas pipelines. Designed for groups of 10-15 participants, this interactive training…

On-Site Training Request

We have conducted on-site training for oil and gas companies for over 25 years and can provide customized workshops for companies with groups of five or more.

We would welcome the opportunity to discuss our services with you.

Sincerely,

W. R. (Bill) Byrd, PE
President
RCP Inc.